Gov’t reports on the federation: Kariba, Zimbabwe
By Benjamin Bradlow, SDI secretariat
The Zimbabwean Homeless People’s Federation, along with support NGO Dialogue on Shelter, met last month with Kariba council officials. This was not unusual in and of itself.
But often the documentation of such engagements falls to the federation and support NGO. So it was a welcome turn of events that the Kariba council itself submitted a report on last month’s meeting. The report lays out some of the possibilities and challenges facing many local councils working with the ZHPF. The same could, in fact, also be said for similar kinds of partnerships of slum dweller federations and local governments in other countries.
The full report, signed by Kariba’s director of housing, is as follows:
Homeless People’s Federation landed in Kariba in April 2001 when they were allocated stand number 2561 Batonga to construct a model house. This allocation was actually a test case meant to gauge the effectiveness of the Federation and its capacity to deliver houses. In 2002 the model house was completed. The Federation managed to construct the required model house within the stipulated time. This proved a point to the Municipality and built confidence in the corporate body.
In March 2004 they were offered 136 stands. These were unserviced but surveyed. The Federation paid for the Engineering designs specifically for the area they were allocated. The Federation members provided labour for the servicing of these stands and they were getting technical assistance from the Dialogue on Shelter and Housing People of Zimbabwe. They successfully completed the servicing of the allocated stands and now they are putting up super structures.
The Municipality further allocated them an additional 12 stands in the same area to cater for extra membership and these successfully serviced and they are now putting the structures.
Then in October 2007 we offered them 52 stands in Batonga 2 and they are currently servicing the stands. In August 2006 they came to council with a request to construct temporary structures whilst developing their permanent houses. Council acceded to this request on the condition that as soon as the developer has completed or partially completed the main house, the temporary structure is demolished. We urge the leadership of the federation to observe this condition.
As council we are very glad that we have found reliable partners in Housing development. The Homeless People’s federation, Dialogue on Shelter and Housing people of Zimbabwe have proved beyond reasonable doubt that they are a reliable vehicle for providing housing/shelter to the poor, not only in Zimbabwe but beyond borders and all local authorities are proud of their work. The hopeless in terms of acquiring shelter have been converted to the hopeful actually reinforcing the concept that “A nation should be a beacon of hope”. The poor widows, orphans ,vulnerable and fully complemented families have been empowered through the provision of their own shelter. As Council we are proud of that.
The Homeless People’s Federation is also into herbal medicines, a venture which actually assist the vulnerable and less privileged members of society in that they cut on medical care. On top of that some of their herbs have proved to be more than modern medicines we get from the shelves of our pharmacies.
CHALLENGES
- Five stands in Batonga are affected by the ZESA power lines and the Council and the Homeless People’s Federation are working together and to rectify this as US6,000.00 is needed by ZESA to divert the power line.
- The terrain, the area the Federation is servicing has got an unfriendly terrain. It is rugged and rocky. Council does not have adequate equipment to assist the members. Currently our backhoe, back actor is down, it need to be repaired.
- Council does not have dozer to assist in the opening of roads. What we have is a grader.